Alexco Announces Second Quarter 2020 Results, Provides Interim Operations Update
VANCOUVER, BC, Aug. 12, 2020 /CNW/ – Alexco Resource Corp. (NYSE American: AXU) (TSX: AXU) (“Alexco” or the “Company”) today reports financial results for the three and six month periods ended June 30, 2020 (“Q2 2020” and “YTD 2020”) and provides interim comments on capital development progress at Keno Hill in anticipation of silver production in Q4 2020. For Q2 2020 Alexco reported a net loss of $12.2 million (“M”), or $0.10 per share related primarily to non-cash items and other adjustments. At June 30, 2020, the Company had $17.8 M in cash and cash equivalents, and net working capital of $24.4 M. Subsequent to quarter end the Company completed an equity financing with aggregate gross proceeds of $30 M.
With an increasing workforce and expanding capital development activity on site, Alexco’s primary focus continues to be the health and safety of our employees, contractors and the communities in which we operate. Our COVID-19 management plan continues with strict prevention measures in place, consistent with the guidelines of the Yukon Government and health officials.
June 24, 2020 the Company announced that it is moving forward to finalize development of its mines at Keno Hill, with a goal of mill commissioning and silver concentrate production in Q4 2020. Generally the Company is making steady progress towards its production goal with mine site development activities, recruitment of key personnel, securing and delivery of mine equipment and advancing capital infrastructure projects at the mill and across the surface operations footprint including camp expansion and mine surface support facilities – all proceeding as scheduled.
Underground activities are currently focused on rehabilitation of the primary access ramp and services installation at the Bellekeno mine, which will be the first mine to deliver ore to the mill in Q4 2020. Initial underground work at Flame & Moth also began in August with minor rehabilitation followed by resumption of ramp development, and similar work will begin at Bermingham later in September. Related to the underground work, new equipment comprising two 3.5 yard Load, Haul, Dump loaders (LHD’s), two 20 tonne haul trucks and two twin boom jumbos have arrived on site, and additional equipment will be delivered consistent with the underground development schedule.
Major mill modifications and improvements underway include the installation of a second ball mill (7′ x 10′), a second tailings filter press, two new concentrate regrind mills for both the lead and zinc concentrate, an improved fine ore feed system, and a crusher ventilation system including a new building enclosure around the existing crusher. All major process equipment has been delivered to site and completion of key mill improvement projects is anticipated with mill commissioning in Q4 2020.
The current focus of surface construction activities is the completion of camp expansion facilities including two new bunkhouse units, an upgraded administration complex, employee dry and wash facilities and maintenance and support facilities. Similar to the mill modification and construction activity, surface construction projects will be complete in Q4 2020.
Na-Cho Nyak Dun. Alexco’s recruiting efforts continue to prioritize residents of the Yukon first along with British Columbia. To date, over 90% of Keno Hill employees are from the Yukon and British Columbia.
July 17, 2020 and is expected to include a minimum of 4,200 meters (“m”) of surface drilling focused on the Bermingham “deep target”, where exploration drilling in 2019 successfully confirmed the presence of wide, high-grade mineralization at depth below the Bermingham high grade silver mineral resource. To date approximately 930 m of drilling is complete utilizing a single drill with a second drill to be added in the near future. Results from this drilling will be released when available.
Clynt Nauman, Alexco’s Chairman and Chief Executive Officer, commented, “The second quarter of 2020 saw us finally receiving our draft (subsequently finalized) renewed and expanded Water Use License for Keno Hill, clearing the way for our positive production decision. Quickly following, we successfully completed a final equity financing, which now positions us with a short runway to production in a rapidly improving silver pricing environment. We look forward to delivering the first ore to the mill and concentrate sales in Q4 of this year. Frankly, with vastly improved silver prices there could be no better time, coincidence or not, to be putting Canada’s only primary silver producing operation on-line. Finally, with production now clearly in sight we are standing at the threshold of a new chapter in Alexco’s journey, focused even more acutely on generating enhanced value for our shareholders.”
www.alexcoresource.com and on SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml.” data-reactid=”46″>Full details of the financial and operating results for Q2 2020 are described in Alexco’s interim condensed consolidated financial statements for the three and six month periods ended June 30, 2020 with accompanying notes and related management’s discussion and analysis. These documents and additional information about Alexco, including its annual information form, are available on Alexco’s website at www.alexcoresource.com and on SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml.
3:00 p.m. Eastern (Noon Pacific) on Thursday, August 13, 2020. To participate in the live call, please use one of the following methods:
Dial toll free from Canada or the US: |
1-800-319-4610 |
Dial from outside Canada or the US: |
1-604-638-5340 |
Conference ID#: |
Ask to join the Alexco conference call |
Live audio webcast: |
|
Participants should connect five to ten minutes before the call. The conference call will be recorded and an archived audio webcast will be available at https://www.alexcoresource.com/ |
Alan McOnie, FAusIMM, Vice President, Exploration, while that regarding mine development and operations has been reviewed and approved by Neil Chambers, P.Eng., Chief Mine Engineer, both of whom are Qualified Persons as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”).
Canada’s Yukon Territory, one of the highest-grade silver deposits in the world. Alexco is currently advancing Keno Hill to production and expects to start concentrate production and shipments in Q4 2020. As per Alexco’s 2020 pre-feasibility study, Keno Hill is expected to produce an average of approximately 4 million ounces of silver per year contained in high quality lead/silver and zinc concentrates. Total production over an 8-year mine life is estimated at 1.18 million tonnes of ore at an average rate of 430 tonnes per day at an average grade of 805 grams per tonne. Keno Hill retains significant potential to grow and Alexco has a long history of expanding the operation’s Mineral Resources through successful exploration.
http://www.prnewswire.com/news-releases/alexco-announces-second-quarter-2020-results-provides-interim-operations-update-301111394.html” data-reactid=”70″>View original content:http://www.prnewswire.com/news-releases/alexco-announces-second-quarter-2020-results-provides-interim-operations-update-301111394.html
SOURCE Alexco Resource Corp.
http://www.newswire.ca/en/releases/archive/August2020/12/c6497.html” data-reactid=”91″>View original content: http://www.newswire.ca/en/releases/archive/August2020/12/c6497.html