Turquoise Hill takes Rio Tinto to arbitration over Mongolia mine funding
The Rio Tinto-controlled company and mine operator had expected the underground expansion to cost $5.3 billion when it was approved in 2015. Last year, however, Turquoise Hill flagged stability risks associated with the original project design, adding that amendments to it could increase costs by as much as an additional $1.9 billion.
Turquoise also warned at the time of further delays of up to two and a half years, with first sustainable production from Oyu Tolgoi’s underground expansion expected between May 2022 and June 2023.
Rio Tinto had said in September it planned to raise up to $500 million through additional lending to develop the giant copper mine. The move, Rio said, would reduce the remaining funding requirement of the expansion to up to $1.4 billion.
By reprofiling, the parties sought more time to repay their debt, knowing that the principal of the extended debt, or in some cases even the interest rate on it, are not reduced.
Any remaining funding for the underground mine, Rio vowed, was to be met through a Turquoise Hill equity offering.
The Vancouver-based miner said late on Wednesday that the proceeding, which was started in British Columbia, followed recent discussions with Rio Tinto relating to the reprofiling.
It also said it would be between three and five months before the parties hear the results of the arbitration, which Turquoise expects it to be a binding decision.
BMO Metals and Mining analyst Edward Sterck criticized Turquoise’s move. “It appears that Turquoise Hill wants Rio Tinto to backstop additional debt or a streaming agreement, which in our view is not in Rio Tinto’s best interests,” he wrote on Thursday.
The expert said both options would leave Rio carrying all the risk at a capital cost likely higher than a direct equity funding option.
Mulling options
Turquoise is simultaneously advancing its evaluation of financing options for Oyu Tolgoi. Such alternatives include additional debt from banks or international financial institutions, an offering of global medium-term notes and a gold streaming transaction, it said.
The company had previously disclosed it was facing a funding shortfall for Oyu’s expansion of up to $4 billion, including balance sheet servicing costs.
BMO Capital Markets expects Turquoise Hill to be short between $1.5 and $2 billion, even before the $500 million the miner and Rio Tinto are hoping to secure.
The company noted it would present Rio with details of the preferred funding options for its consideration before the end of the year.
Once completed, the underground section of Oyu Tolgoi will lift production from 125,000–150,000 tonnes in 2019 to 560,000 tonnes at peak output, which is now expected by 2025 at the earliest. This would make it the biggest new copper mine to come on stream in several years.
Oyu Tolgoi, located in the South Gobi desert near the border with China, produced 35,203 tonnes of copper and 26,154 ounces of gold in the first three months of this year.
Rio Tinto owns the mine through its majority stake in Turquoise Hill, which has a 66% interest in Oyu Tolgoi. The Mongolian state has the remaining 34% in the operation.