Thor expects first gold pour at Segilola by end of July

Remaining work on the project is focused primarily on the gold room, elution and electrowinning circuit, power connection, instrumentation and control installations, the company added.

The process plant is being commissioned in phases, with commissioning having already started at the power plant. Commissioning of the SAG & ball mills and the crushing section will follow.

Thereafter, commissioning will continue with the remaining areas of the process plant.

Mining is currently underway, with 700,000 tonnes of waste mined and 30,000 tonnes of ore stockpiled in preparation for process plant commissioning. The pit is fully prepared for mining operations, with pre-strip nearing completion.

The mining fleet is now fully commissioned, and production is expected to quickly ramp up to its design capacity, Thor stated in Monday’s news release.

All the necessary permits are in place and blasting operations have started as the company moves into the harder transitional and fresh ore zones.

Shares of Thor Explorations were down 9.0% by 11:30 a.m. in Toronto. The Africa-focused gold miner has a market capitalization of C$186.9 million.