Millennial Lithium commissions lithium carbonate pilot plant at Pastos Grandes project
According to Millenial, pilot ponds filled with brine pumped from the central part of the project and in operation since late 2018, are at the required concentration to provide lithium-rich brine concentrate to the pilot plant
“Despite covid-19 restrictions and minor delays, the Millennial team has advanced the lithium concentration ponds and the pilot plant to the production stage. Evaporation ponds have been concentrating lithium and plant feed,” Farhad Abasov, the company’s president and CEO, said in the media brief. “The first stage of the plant, the Solvent Extraction (SX) unit to remove boron, has been installed and tested. The first output of battery-grade lithium carbonate is planned for Q4-2020 marking another significant milestone for the company.”
Abasov said that, at present, the pilot plant is being fed with concentrated lithium-rich brine from the smaller feeder ponds which had reached a grade of 2.7% Li, and expected to reach the target 3% Li with naturally reduced impurities by the time the full flow sheet is commissioned.
Located in the northwestern part of Argentina, Pastos Grandes covers over 12,619 hectares. To date, Millennial has invested more than C$40 million in exploration and development work on the property, which includes 22 completed exploration/monitoring wells, four pumping test production wells, pilot ponds, the pilot plant as well as a year-round camp supported by a hybrid solar power system.