Using a base case gold price of $1,500/oz, the project has an after-tax net present value (NPV) discounted at 5% of $305 million with an internal rate of return (IRR) of 58%.
“We continue to deliver on our sector-leading growth by launching into full construction at Santa Luz, after pouring first gold at our Castle Mountain mine less than a month ago and first gold at our Aurizona mine only 15 months ago,” Equinox CEO Christian Milau stated in a press release.
“With initial capital of only $103 million, Santa Luz is fully funded and will start contributing significant cash flow to the company in just over one year’s time,” Milau added.
As a brownfields past-producing mine, the majority of site services and infrastructure at Santa Luz is already in place. The initial capital costs to restart the mine include refurbishing existing infrastructure, retrofitting the plant, installing additional grinding power, and increasing the storage capacities of the existing tailings and water storage facilities.
Open-pit stripping is expected to begin in February 2021. Modifications and upgrades to the processing plant and tailings and water storage facilities are expected to be finished by the end of 2021, with first gold pour targeted for Q1 2022.
Meanwhile, Equinox has also resumed exploration in the highly prospective Santa Luz-Fazenda district, a 70 km long greenstone belt that extends between the company’s two mines in Bahia state.